- PILING WORK - EMPTY BORING THROUGH ALL KINDS OF SOILS INCLUDING HARD MURRUM WITH GRAVEL AND ROCK FRAGMENTS.
- CONSTRUCTION OF BORED CAST-IN-SITU PILES INCLUDING BORING THROUGH ALL KINDS OF SOILS INCLUDING HARD MURRUM WITH GRAVEL AND ROCK FRAGMENTS.
- TRANSPORTING, HANDLING, CLEANING, CUTTING, BENDING, TACK WELDING LAP JOINTS IN LONGITUDINAL BARS, ASSEMBLING, TYING, BINDING WITH SOFT ANNEALED 16 GAUGE BINDING WIRE, PLACING IN POSITION HYSD CRS BARS UPTO 12mm DIA AT ALL LEVELS.
- CARRYING OUT PILE INTEGRITY TEST CONFORMING TO IS SPECIFICATIONS. CARRYING OUT DYNAMIC LOAD TEST, INITIAL CYCLIC LATERAL AND INITIAL CYCLIC VERTICAL TESTS CONFORMING TO IS SPECIFICATIONS.